Complementation and Implantation Works for Teresópolis brewery’s factory.
About The Work
The executed Project included the whole needed infrasctructure for the factory’s implantation, such as intern and access way pavement, storm sewer drainage system, industrial wastewater treatment construction, electricity, telephony and force network installations, stacking with micropile and precast concrete, reinforced concret laser levelled (laser-induced breakdown spectroscopy) floor’s execution, security cabin construction at the main entrance, infrastructure execution for the factory’s area ampliation, earthwork execution, access clover’s drainage and pavement at BR-116 highway, prolongation of the street gutter’s crossing’s river with sewer concrete pipe gallery with section 2,00 m x 2,00 m.
Built Area
M²